PGI completed a construction project at an eight-acre high-security U.S. Department of Homeland Security Air and Marine Operations facility at the March Airforce Base. The project scope included the installation of light poles, LED lamps, fixtures, and a complete security camera system.
Various elements of the project included:
• Underground excavation and laying of conduits for cameras and lighting systems
• Backfill, compaction and patching of trenches
• Installing 17 light poles on concrete pole bases with 34 LED light fixtures
• Performing work on live 480 Volt electrical panel
The project was completed ontime and within budget, with no safety incidents or disruptions.
Very good to Excellent rating on the PPQ.